News
Carpetright Tamworth
- Details
- 17 December 2018
Complete refurbishment of the store in four phases:-
1st Phase
- Take down existing warehouse wall and reconstruct new installation and re-configuration of warehouse racking
2nd Phase
- Remove all flooring and fixtures and fittings from specialist flooring area and reinstate new.
- Form new curved special display wall
- Complete redecoration of store
- Extend existing suspended ceiling
- Complete refurbishment of amenity block
- Up lift and relay flooring to main sales area
- Form new laminate and soft flooring area including
- New flooring and installation of new fixtures and fittings
3rd Phase
- Remove all existing lighting and replace with new
4th Phase
- New signage internal and external
Contract duration 4 weeks completed on time and on budget.
Entrance
BEFORE AFTER
Specialist Carpet Section
BEFORE AFTER
Main Sales Area
BEFORE AFTER
Soft Flooring and Laminate
BEFORE AFTER
Carpetright Rugby
- Details
- 10 October 2017
New store - projected to start on 31st Oct 2017
Carpetright Sheffield Meadow Hall
- Details
- 04 October 2017
Minor refurbishment:
- Reposition of warehouse wall
- New stockroom racking
- Upgrade to the bed area
- Redecoration of the store
- Re-spray of the shopfront
Carpetright Whetstone
- Details
- 27 September 2017
Minor refurbishment including a replacement of special display area.
Carpetright Stockton-on-Tees
- Details
- 21 September 2017
Minor refurbishment had been completed.
The works included:
- New laminate area
- Replacement of all sales area carpets
- Upgrade to the toilets block
- Re-spray of the shopfront
Photos of the refurbished store below: