Refurbishment of Carpetright Swindon, Wiltshire

Project Details:

Commenced 9th May 

Completed: 4th June

Scope of works:

  • Major refurbishment of store including as follows
  • New bed area complete with new ceiling, flooring, lighting and decoration
  • Extend the existing premier carpet sales area
  • New laminate department
  • Alterations to warehouse partitioning inc new doors
  • Complete overhaul of toilet block
  • Complete redecoration of external cladding and re spraying of all windows and doors
  • All new signage

Photos from BEFORE (the photos after the renovation coming soon...)

swindon1     swindon2

swindon3     swindon5

News

Carpetright Tamworth

December 2018
Complete refurbishment of the store in four phases:- 1st Phase Take down existing warehouse wall and reconstruct new...

Projects Gallery

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8

logo-blueIf you have any questions please contact us on 01543 466653 or email us.