Carpetright refurbishment Orpington 4

Scope of work:

  • Strip out all existing flooring
  • Line out walls
  • New laminate area
  • Removal of existing office
  • Cut back existing suspended ceiling
  • Install new suspended fascia
  • New remnant racks
  • New flooring throughout
  • Electrical works
  • New signage
  • Jet wash external cladding


Work commences on 30th November 2015. Completion date: 13th December 2015. 